Punta Catalina​ – Dominican Republic

For the new greenfield Coal Power Plant of Punta Catalina,​ Santo Domingo, Bedeschi supplied a Complete Material Handling equipment set from coal receiving rail Mobile Hopper on jetty up to coal storage and delivery up to loading point at boiler area.​

The total plant capacity is 2×360 MW.​ Main characteristic of this supply is a 3000 tph capacity 2150 m long pipe conveyor (D.700 mm)​.

Project environmental conditions constrained and lead to an extremely challenging design phase of equipment and structures due to very heavy wind (hurricane & tsunamis area), soil (instability & potential liquefaction) and earthquake conditions.