BLOG

SECIL Outão Cement Plant updates

Site update from the SECIL Outão Cement Plant in Portugal where Bedeschi is in the cold commissioning phase of a new pipe conveyor to handle different kind of alternative fuels.
The pipe conveyor has a diameter of 250mm and conveying length of 350m and will grant a safe and clean transportation of alternative fuels at a rate of 300m3/h. SECIL CCL (Cement Clean Line) project, aims to bring the Outão cement plant to the forefront of energy efficiency and lowest CO2 emissions among the European cement producers.